Tuesday, January 10, 2012

Reminder

In case you need a reminder of why we're reconstructing this bunker, here's a shot from 2007.  This is what you get when a bunker is built with a high flashing face but the green design allows water to run right over the top edge of the bunker instead of being diverted around it.

Monday, January 9, 2012

NEXT? Front Bunker on #10

Today Alex started work on renovating the right front bunker on #10.  This will be simlar to what was done to the bunker on #1;  the steep face will be replaced with a sod face and a smaller, flatter bunker.

"BEFORE":













A little movie of Alex excavating








Monday, December 12, 2011

ALMOST DONE!

Sodding is almost done and now you can see what the new bunker on #1 will look like.  No more steep faced, washed out, always a mess bunker!




Bunker on #1 - Progress!

Work continues toward completion of the right front bunker on hole #1. The drain is in, covered by pea gravel, and today we filled the bunker with new sand and began the sodding process.
More sand has been added.   You can also see the layers of sod that are being laid around the edge.




Another view of the bunker, now full of sand, and the sod work that is going on around it.


Because we are using sod that has been harvested from other places on the course, and we are running out of good places to do that, we are only going to sod the inner and outer edges of the turf area for right now.  The area between will be seeded this afternoon and covered with a protective cover like has been used on the practice green. 

Friday, December 2, 2011

Bunker work continues

Work continues on the right front bunker on hole #1.  The major shaping is completed and in the first three pictures below the white outer line indicates the approximate shape that will eventually be the sand portion of the bunker.  Everything outside that line will be sodded with grass.  The white line you see through the center of the oval is where the drain will be installed.

Looking over the bunker to the green, everything inside the white line will be sand.  Outside the white line will be grass.  The white line through the center indicates the drain location.

Another view of the reshaped bunker.  Notice that we've also added a small berm to the upper side of the shape to aid in diverting water away from the bunker.
And another view, looking back toward the fairway.  The berm is also evident in this photo.




The excavator is used to dig out a pocket for the area that will be the sand portion of the bunker.




Another view of the excavated area with the drain ready to install

Tuesday, November 29, 2011

Bunker on #1

Today Alex and his crew began the reconstruction of the right front bunker on hole #1.  Who among you hasn't wanted to do this at some time?


The design of this bunker with the steeply flashed faces caused on-going maintenance issues for us.  Every time we had a hard rain water would run off the green and down the face of the bunker, washing the sound out and exposing the soil below it.  In time the soil mixed with the sand, contaminating it so that it would not drain and become more "dirt" than "sand".   Our modification is going to involve sloping the bunker sides more, and covering them with sod (grass) rather than attempting to keep sand flashed up on them.  The result will be a bunker that isn't subject to the wash-out problems that it has been up to this point.

Visit YouTube http://www.youtube.com/watch?v=ifXv6SpCL1I&feature=youtube_gdata for a short video of the excavation.


In the picture above you can see that the drain is nearly three feet below the surface.  It should be only a few inches under the sand.  Repeated wash outs actually resulted in restructuring of the bunker.

 


In the above photo you can see the new shape is beginning to take form.  The load of dirt you see being dumped, along with several more loads, will be used to create a slight berm around the upper lip of the bunker.  This will also help divert water from running into the bunker.
The red outline drawn on the picture is the approximate size and location of the sand portion of the bunker.  The areas outside the red line will be sodded with zoysia.



A slightly different view of the mostly finished bunker.  The black pipe you see is the drain tile.  Once final shaping is completed new drains will be excavated in the bottom of the bunker and attached to this drain pipe.




Friday, September 9, 2011

green repairs

Everyone knows that the extended heat this summer was hard on golf greens throughout the midwest.  Despite our best efforts, Lake Valley did not escape untouched either.  Today, Alex and his crew were busy stealing sod from the lower level of the practice green to replace the worst spots on about three of our greens.  They started today by patching in sod into the worst spots on #14 green, and will continue the process next week on greens #9 and #15.

Why don't they seed it, you ask?  Actually, we did.  Twice.  Unfortunately, each time the seed germinated and just began to grow we were hit with another series of 100-degree weather and the new plants simply weren't strong enough to survive.  To counter that, Alex decided to go with "instant gratification" by laying in sod on the worst spots.  Another problem with growing from seed is that you almost need to close the green to allow the new grass to properly mature, an option that really isn't available to us.

I'm posting a few pictures from Friday afternoon to give you an idea of what is happening:

click picture for larger image
In the above picture you can see some of the sod that has been stripped in, as well as some plugs that were taken from the outer perimeter of the green.


(Above) Alex is spreading a light coat of sand on the seams and lower areas of the patched green.  These will be broomed in similar to a very light top dressing.



Above you see Kevin and Kelly taking plugs from the back outer edge of the green and replacing small areas, while Alex is spreading a light sand dressing and Jay uses a soft bristle broom to sweep the sand in.  After his process was finished they ran the vibratory rollers over the green to smooth everything as much as possible.  On Monday the entire green will receive a full top dressing.

.